Release date: 19 September 2011
Promoter – Financial Intermediary
Moroccan Agency for Solar Energy ("MASEN")Location
Description
The 500 MW Ouarzazate complex is the first project launched under the Moroccan Solar Plan. It will be developed through different successive phases. The project is the first phase of the complex and will follow the Independent Power Producer model already implemented in Morocco. It is expected to comprise one thermal solar power plant with a production capacity between 125 and 160 MW, with a minimum of around 450 MWh of thermal storage. The project is scheduled to begin operation in early 2014.
Objectives
The Moroccan Solar Plan is one of the six concrete projects of the Union for the Mediterranean, launched by the Euro-Mediterranean Heads of State and Government during the Paris Summit, held on 13th July 2008, to promote the production and use of renewable energies (more specifically, turning the Mediterranean partner countries into producers and exporters of solar energy).
Comments
This operation is covered by the EU Guarantee for EIB loans outside the EU.
Sector(s)
- Energy - Electricity, gas, steam and air conditioning supply
Proposed EIB finance (Approximate amount)
EUR 100 million
Total cost (Approximate amount)
EUR 676 million
Environmental aspects
If the project were located within the EU, it would fall under Annex II of the EIA-Directive (85/337/EEC) as amended. In line with national legislation (EIA Law No.12-03), the promoter intends to follow an EIA procedure for the project. A scoping environmental and social study has been prepared for the whole Ouarzazate complex, and the promoter will require that the successful bidder for the first phase (i.e. the project) performs an EIA. Details of the Environmental procedures to be carried out, including possible impacts on any sites of nature conservation importance, will be investigated further by the Bank during appraisal to ensure that the project complies with the Bank's principles and standards as regards environmental and social issues.
Procurement
Within the EU, the promoter, being a public contracting authority, would be subject to public procurement procedures according to 2004/17/EU, including publication of contract notices in the Official Journal of the EU. In line with the Bank's principles and its statute, the promoter is following the provisions of the Bank's Guide to Procurement, which includes amongst others international competitive bidding and Official Journal of the EU contract notice publication for the items to be financed by the Bank.
Status
Signed - 19/11/2012
Disclaimer