    Financing of signaling & telecommunication schemes under a public-private partnership (PPP) contract for the high speed infrastructure between Albacete and Alicante.

    Objectives

    Development of the detailed design of the project components – traffic control, fixed and mobile communications, and safety equipment. Execution of the construction works, including equipment testing.

    Sector(s)

    Proposed EIB finance (Approximate amount)

    EUR 110 million

    Total cost (Approximate amount)

    EUR 265 million

    Environmental aspects

    According to EU Directive 85/337/EEC amended by 97/11/EC and 2003/35/EC, the overall high-speed rail link project falls into the Annex I category and therefore an EIA is mandatory. Compliance with national and EU environmental legislation as well as potential impacts on Natura 2000 network will be verified during appraisal. The project planning predates the SEA Directive 2001/142/EC. The works included in this particular contract do not fall into Annex I nor II of the above mentioned Directive and consequently no EIA is required.

    Procurement

    The PPP project will be procured under a competitive dialogue process. The contracting authority is a public promoter obliged to comply with the relevant applicable EU project legislation (EU directive 2004/18) and National Public Procurement legislation. The Bank will require the Promoter to ensure that contracts for the implementation of the project have been tendered and awarded in accordance with this legal framework and will review the awarded tender in this regard.

    Status

    Signed - 25/05/2012

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    Related tags

    Spain Transport