Release date: 10 May 2011
Promoter – Financial Intermediary
Iberdrola SA
Location
Description
Reinforcement and extension of the electricity distribution network in Spain, mainly in convergence areas, in the year 2011.
Objectives
The project will enable the promoter to improve the reliability, and quality of electricity supply in Spain. The project will also cater for a demand growth of circa 1.5%, reduce losses, and improve safety performance. About 60% of the project will be implemented in areas designated as convergence, phasing-in and phasing-out regions.
Sector(s)
Proposed EIB finance (Approximate amount)
EUR 200 million
Total cost (Approximate amount)
EUR 440 million
Environmental aspects
The project includes 32 schemes that do require Environmental Impact Assessment. EIAs are being carried out in accordance with applicable legislation in line with the EU EIA Directive. The impacts that can be typically expected for these schemes relate to visual impact, vegetation clearance and impact on flying vertebrates, electromagnetic fields, noise nuisance, and disturbance during construction. Most of the project schemes relate to medium and low voltages and are therefore expected to have minimal or null environmental impacts.
Procurement
The promoter is a contracting entity that falls under the Utilities Directive 2004/17/EC, and is therefore required to tender works, supplies and services contracts following public procurement rules, including the publication in the Official Journal of the EU (OJEU) where appropriate.
Status
Signed - 23/11/2011