sConstruction of a gas pipeline between Klaipeda and Kursenai
Objectives
The project consists of the construction of a 110 km long DN800 gas pipeline and a maximum operating pressure of 54 bar, from Klaipeda up to Kuršenai. The project will allow the capacity enhancement of Klaipeda-Kiemenai pipeline in Lithuania.
Sector(s)
- Energy - Electricity, gas, steam and air conditioning supply
Proposed EIB finance (Approximate amount)
EUR 28 million
Total cost (Approximate amount)
EUR 59 million
Environmental aspects
The project required an environmental impact assessment (EIA), which has already been approved by the competent authority.
Procurement
The investment is subject to the procurement provisions defined in Directive 2004/17/EC for entities operating in the water, energy, transport and postal services sectors.
Status
Signed - 21/12/2015