Release date: 30 November 2016
Promoter – Financial Intermediary
SC APA CTTA SALocation
Description
Financing Alba County regional operator's contribution during the 2014-2020 programming period to the investment programme funded by the Large Infrastructure Operational Programme
Objectives
This project will improve and extend the water supply and sanitation infrastructure in Alba County, within the Large Infrastructure Operational Programme 2014-2020, in order to accelerate the process of complying with Romania's commitments in the EU Accession Treaty and bringing the sector in line with the standards set by Directive 91/271/EEC and Directive 98/83/EC.
Sector(s)
- Water, sewerage - Water supply; sewerage, waste management and remediation activities
Proposed EIB finance (Approximate amount)
EUR 12 million
Total cost (Approximate amount)
EUR 114 million
Environmental aspects
The project is expected to have a significant positive environmental and public health impact and contribute to meeting the country's needs in the water and sanitation sector, in relation to compliance with EU environmental legislation.
Procurement
The Bank will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Directive 2014/25/EU as well as Directives 89/665/EEC and 92/13/EEC) as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the EU, as and where required.
Status
Signed - 20/02/2019
Disclaimer
Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).