    Référence: 20220716
    Date de publication: 16 mai 2024

    Promoteur – Intermédiaire Financier

    JSC ELEKTROPRIVREDA SRBIJE BELGRADE

    Lieu

    Description

    Rehabilitation of several large hydropower plants, construction of a 13 megawatt new hydro unit at the Potpec hydroelectric power plant , development and implementation of greenfield renewables

    Objectifs

    The operation is a framework loan to finance promoter's key green investments for the period 2024-2030 with a view to increase ultimately the national share of renewables to the target set by 2030. The project tentatively consists of i) the rehabilitation of 239 megawatt (MW) power units in of three hydropower plants (Bistrica hydroelectric power plant (HPP), Potpec HPP and Djerdap HPP) which are totalling 428 MW, ii) the construction of a new 13 MW unit at Potpec HPP, iii) several greenfield renewables of which more than 120 MW solar plants and iv) the rehabilitation of 129 MW Vlasinske hydropower cascade.

    Secteur(s)

    • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

    Under Global Europe NDICI guarantee

    Under EFSD+ Guarantee

    Montant BEI envisagé (montant approximatif)

    EUR 200 million

    Coût total (montant approximatif)

    EUR 408 million

    Aspects environnementaux

    The construction of new hydropower unit would fall under Annex I while the rehabilitation of hydropower units and other small components would usually fall under Annex II of the Environmental Impact Assessment (EIA) Directive 2014/52/EU, amending the EIA Directive 2011/92/EU. The latter Annex II components would require the competent national authority to determine the need for an Environmental Impact Assessment Environmental authorisation has been delivered to Djerdap II HPP rehabilitation. Bistrita HPP was screened out in 2019 by the competent Authorities. The Promoter resubmitted the project to the competent Authority as the scope had slightly increased from the original design. Potpec HPP rehabilitation received its authorisation in 2018. Due to changes in the project (construction of an additional unit IV), the Promoter is carrying out the EIA to be sent to the Competent Authorities in 2024 to obtain the environmental authorisation and the subsequent building permit. Based on preliminary information received, the project components are unlikely to entail any substantial adverse environmental or social impacts. The Bank will review the project's potential environmental and social impacts in line with its Environmental and Social Sustainability Framework upon new allocation request under the framework loan.

    Passation des marchés

    The Bank will require the promoter to ensure that implementation of the project will be done in accordance with the Bank's Guide to Procurement and the relevant applicable EU public procurement rules. The promoter Elektroprivreda Srbije (EPS) is a state-owned electric utility company. Public procurement procedures as set in the Bank's Guide to Procurement will apply.

    Statut

    Approuvé - 21/06/2024

    Milestone
    À l'examen
    Approuvé
    21 juin 2024

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Serbie Énergie