    Referenz: 20220716
    Veröffentlichungsdatum: 16 Mai 2024

    Projektträger – zwischengeschaltetes Finanzinstitut

    JSC ELEKTROPRIVREDA SRBIJE BELGRADE

    Ort

    Beschreibung

    Rehabilitation of several large hydropower plants, construction of a 13 megawatt new hydro unit at the Potpec hydroelectric power plant , development and implementation of greenfield renewables

    Ziele

    The operation is a framework loan to finance promoter's key green investments for the period 2024-2030 with a view to increase ultimately the national share of renewables to the target set by 2030. The project tentatively consists of i) the rehabilitation of 239 megawatt (MW) power units in of three hydropower plants (Bistrica hydroelectric power plant (HPP), Potpec HPP and Djerdap HPP) which are totalling 428 MW, ii) the construction of a new 13 MW unit at Potpec HPP, iii) several greenfield renewables of which more than 120 MW solar plants and iv) the rehabilitation of 129 MW Vlasinske hydropower cascade.

    Sektor(en)

    Under Global Europe NDICI guarantee

    Under EFSD+ Guarantee

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 200 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 408 million

    Umweltaspekte

    The construction of new hydropower unit would fall under Annex I while the rehabilitation of hydropower units and other small components would usually fall under Annex II of the Environmental Impact Assessment (EIA) Directive 2014/52/EU, amending the EIA Directive 2011/92/EU. The latter Annex II components would require the competent national authority to determine the need for an Environmental Impact Assessment Environmental authorisation has been delivered to Djerdap II HPP rehabilitation. Bistrita HPP was screened out in 2019 by the competent Authorities. The Promoter resubmitted the project to the competent Authority as the scope had slightly increased from the original design. Potpec HPP rehabilitation received its authorisation in 2018. Due to changes in the project (construction of an additional unit IV), the Promoter is carrying out the EIA to be sent to the Competent Authorities in 2024 to obtain the environmental authorisation and the subsequent building permit. Based on preliminary information received, the project components are unlikely to entail any substantial adverse environmental or social impacts. The Bank will review the project's potential environmental and social impacts in line with its Environmental and Social Sustainability Framework upon new allocation request under the framework loan.

    Auftragsvergabe

    The Bank will require the promoter to ensure that implementation of the project will be done in accordance with the Bank's Guide to Procurement and the relevant applicable EU public procurement rules. The promoter Elektroprivreda Srbije (EPS) is a state-owned electric utility company. Public procurement procedures as set in the Bank's Guide to Procurement will apply.

    Projektstatus

    Genehmigt - 21/06/2024

    Milestone
    In Prüfung
    Genehmigt
    21 Juni 2024

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Serbien Energie