Referenz: 20090232
Veröffentlichungsdatum: 14 Februar 2011

Projektträger – zwischengeschaltetes Finanzinstitut

Metropolitan Community of Montpellier (Communauté d'A gglomération de Montpellier)

Ort

Beschreibung

The project consists of the construction of a third 22 km tramway line with 31 stops and the 0.5 km westward extension of Line 1. Line III will cross four municipalities in succession: Montpellier, Lattes, Pérols and Juvignac. The project also includes the acquisition of 23 40m-long tram-sets, each with a capacity of 300 passengers. Urban development and landscaping measures form an integral part of the project.

Ziele

The project consists of the construction of a third 22 km tramway line with 31 stops and the 0.5 km westward extension of Line 1. Line III will cross four municipalities in succession: Montpellier, Lattes, Pérols and Juvignac. The project also includes the acquisition of 23 40m-long tram-sets, each with a capacity of 300 passengers. Urban development and landscaping measures form an integral part of the project.

Sektor(en)

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

EUR 250 million.

Gesamtkosten (voraussichtlicher Betrag)

EUR 530 million.

Umweltaspekte

The project comes under Annex II to Directive 85/337/EEC amended, which stipulates that the competent national authorities must decide whether an environmental impact assessment (EIA) is to be conducted. Under French law, the project is subject to an impact assessment as part of the Declaration of Public Interest (DUP) procedure. This procedure was completed in June 2007 and the project obtained a favourable opinion from the various government departments, including the environmental authority.

Auftragsvergabe

Procurement procedures will be in accordance with national legislation and EU directives.

Projektstatus

Unterzeichnet - 4/07/2011

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

Tags

Frankreich Verkehr