    Referenz: 20090679
    Veröffentlichungsdatum: 20 Januar 2010

    Projektträger – zwischengeschaltetes Finanzinstitut

    Ethekwini Municipality

    Ort

    Beschreibung

    Upgrade and expansion of water infrastructure to improve the efficiency of the network system (i.e. reduce non-revenue water) and augment capacity. The investments are part of eThekwini's capital expenditure programme for 2010-2014.

    Ziele

    By increasing systems efficiency, delivery, and treatment capacity, this project contributes to assuring the security of supply of potable water to eThekwini Municipality’s customers and increased access to water in unserved areas, thus contributing to the achievement of the Millennium Development Goals in South Africa.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 50 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 180 million

    Umweltaspekte

    The replacement of old pipes included in the project does not require any EIA but the installation is subject to nuisance control measures during construction. The Western Aqueduct consists of a new underground trunk main that was submitted to a full EIA approved by the relevant environmental agency in October 2008. The environmental license – or ROD (Record of Decision) - confirms that the impact can be properly mitigated with minor residual and permanent negative effects. The Northern Aqueduct is still at design stage and will also be submitted to an EIA. The promoter will keep the Bank informed and provide the relevant documents.

    Auftragsvergabe

    The Bank will require the promoter to ensure that implementation of the project will be done in compliance with the Bank’s Guide to Procurement.

    Projektstatus

    Unterzeichnet - 6/12/2010

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Südafrika Wasser, Abwasser