Referenz: 20220496
Veröffentlichungsdatum: 30 September 2022

Projektträger – zwischengeschaltetes Finanzinstitut

CEZ DISTRIBUCE AS

Ort

Beschreibung

An investment programme for CEZ Distribuce's electricity distribution network in the Czech Republic over the period 2023-2024. The programme includes investments in the reinforcement and refurbishment of medium- and low-voltage networks.

Additionality and Impact

The programme comprises investments in the electricity distribution network in the Czech Republic over the period 2023-2024.

It addresses the needs for the renewal of existing assets and planned development, including automation and tele-control.

The programme contributes to maintaining or increasing security of supply by reducing the risk of black outs, and it contributes to the integration of low-carbon generation and thus reduces carbon and air pollution externalities.

The investments contribute to achieving EU and national targets, as set out in the 2030 National Energy and Climate Plan of Czechia. 

100% of the programme will benefit Cohesion regions in the Czech Republic.

Long tenor and flexible financing conditions (drawdown and repayment flexibility) provided by the Bank will help the Promoter achieve the investment objectives. The project has excellent economic rate of return and social benefit and generates additional employment in construction. The capacity of the promoter is considered appropriate for the proposed project. The financing will have also an important signalling effect in times when energy company face significant financing needs.

Ziele

The project will allow the Promoter to maintain the reliability and quality of electricity supply and to integrate renewable energy sources.

Sektor(en)

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

EUR 790 million

Gesamtkosten (voraussichtlicher Betrag)

EUR 1057 million

Umweltaspekte

The programme schemes are expected to have limited environmental consequences. Environmental impact studies will be carried out as applicable and mitigating and/or compensation measures will be applied as necessary.

Auftragsvergabe

The Bank will require the Promoter to ensure that contracts for the implementation of the project have been and will be tendered in accordance with the relevant applicable EU procurement legislation (Directive 2014/25/EU where applicable), as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the EU, as and where required.

Projektstatus

Unterzeichnet - 12/12/2022

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

Tags

Tschechien Energie