    € 173,500,000
    Countries
    Sector(s)
    Morocco : € 173,500,000
    Industry : € 173,500,000
    Signature date(s)
    9/02/2012 : € 31,500,000
    3/09/2012 : € 42,000,000
    22/10/2009 : € 100,000,000
    Link to source

    Summary sheet

    Release date
    23 September 2009
    Status
    Reference
    Signed | 22/10/2009
    20090278
    Project name
    Promoter - financial intermediary
    Renault Tanger-Financement Intermedie
    Renault
    Proposed EIB finance (Approximate amount)
    Total cost (Approximate amount)
    EUR 200 million, on own resources (Mandate ENP MED 2007-2013)
    EUR 700 million
    Location
    Sector(s)
    Description
    Objectives

    The project comprises Renault’s investment in a new car manufacturing facility located in the Melloussa Free Economic Zone (30 km from Tanger harbour). The investment includes the design, civil engineering, purchase of equipment and tooling of the new factory, as well as the construction of an administrative building at the Renault terminal at the Tanger Med Harbour. The investment period is 2009-2012.

    The project aims at setting up a production facility for new models of the promoter’s low-cost brand, mainly for the European and Eastern Europe markets.

    Environmental aspects
    Procurement

    The competent Moroccan authorities required that an EIA be carried out. Since the site was chosen and dedicated to automotive production by TMSA (Tangier Mediterranean Special Agency), the national agency operating the Free Zones in the North of the country, a study of alternative sites could not be conducted by the promoter.

    The land where the plant is located, parts of which were previously used for agriculture, was acquired by TMSA and provided to the promoter for the new plant. The process of land acquisition and expropriation of former owners has been performed in accordance with Moroccan law, including public consultations. As part of the expropriation process that was carried out between 2005 and 2008, TMSA ensured that resettlement was kept to a minimum.

    The promoter is a private company not operating in the utilities sector, and is thus not covered by EU Directive 2004/18/CE. The procurement procedures followed by the promoter (international and local competitive negotiation procedures) are in the best interest of the project and are acceptable to the Bank.

    Comments

    Because this is an intermediated financing operation, the Bank’s intervention also aims at supporting the local financial institutions committed to the financing of the project.

    Link to source

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    News & Stories

    General enquiries and comments

    The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities.
    Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
    Alternatively, the EIB can be contacted through its external offices.
    Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.

    Media enquiries

    Media-related enquiries can be addressed to the EIB Press Office. Please also visit our Media information section.

    Complaints mechanism

    Any complaint regarding alleged maladministration can be lodged via the EIB Complaints Mechanism. The European Ombudsman acts as an independent external accountability mechanism of the EIB.

    Zero tolerance against fraud and corruption

    The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Fraud and Investigation division. All complaints will be treated as strictly confidential and handled in line with the EIB investigation procedures and the Anti-Fraud Policy.