22 September 2020
Status
Reference
Under appraisal | 20/03/2019
20180369
Project name
Promoter - financial intermediary
TULU MOYE GEOTHERMAL IPP PHASE I
MERIDIAM SAS,REYKJAVIK GEOTHERMAL LTD
Proposed EIB finance (Approximate amount)
Total cost (Approximate amount)
USD 59 million (EUR 49 million)
USD 271 million (EUR 228 million)
Location
Sector(s)
  • Energy - Electricity, gas, steam and air conditioning supply
Description
Objectives

Construction of a 50 MW geothermal power plant as a privately developed Independent Power Producer (IPP) in Tulu Moye, Oromia State, Ethiopia, that will provide a capacity increase and diversification of energy resources in Ethiopia.

Investment in geothermal energy will help reduce power outages and meet the rapid growth in demand, and with lower greenhouse gas (GHG) emissions than fossil-fuel-based alternatives, thereby supporting the sustainable economic development of Ethiopia. The project contributes to EU renewable energy and environmental policies (particularly climate change policies) and several Sustainable Development Goals (SDGs), especially SDG 7 - access to affordable and clean energy.

Environmental aspects
Procurement

If located in the EU, the project would fall under Annex II of the EU EIA Directive, requiring a screening decision by the competent authority. In accordance with the Ethiopian Environmental Impact Assessment Proclamation 299/2002, an Environmental and Social Impact Assessment (ESIA) has been carried out, covering the impacts of constructing a 100 MW power plant with associated drilling, steamfield collection and grid connection. The ESIA, which also includes the results from the public consultation and participation, was approved by the Ministry of Water Irrigation and Energy in June 2018 and received clearance in accordance with the Federal Environmental Protection Authority. The key potential adverse impacts identified are involuntary resettlement owing to land use change, noise, air quality, archaeology and cultural heritage sites, landscape and wildlife. The Bank will assess environmental and social aspects during appraisal to check alignment with EIB Environmental and Social Standards. In particular, the Bank will review that appropriate public consultations have been carried out during the ESIA process as well as request a Stakeholder Engagement Plan at the level of the project, inclusive of a Grievance Mechanism. Environmental and social impacts of the project, inclusive of the transmission line, will be appraised in accordance with the Bank's environmental and social standards.

The exploration license has been, and the geothermal well-field development and use license is expected to be, awarded to the Promoter on an exclusive basis. In the absence of competition related to the award of the exploration and operating licenses, the PPA will be reviewed to assess whether it is economically reasonable in terms of price, quality and risk-sharing and the works, goods and services covered by the Bank's financing will be considered as operations in the public sector from a procurement perspective as defined in the EIB Guide to Procurement. The Bank will ensure that implementation of the project will be done in accordance with the Bank's Guide to Procurement.

Related projects
Link to source

Disclaimer

Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

Documents

Resettlement Action Plan (RAP) - TULU MOYE GEOTHERMAL IPP PHASE I
Publication Date
26 Nov 2022
Document language
Main Topic
Lending
Document Number
164339537
Document Focus
Environmental Information
Project Number
20180369
Sector(s)
Countries
Publicly available
Download now
Environmental and Social Impact Assessment (ESIA) - TULU MOYE GEOTHERMAL IPP PHASE I
Publication Date
26 Nov 2022
Document language
Main Topic
Lending
Document Number
164342847
Document Focus
Environmental Information
Project Number
20180369
Sector(s)
Countries
Publicly available
Download now
Other links

General enquiries and comments

The EIB is committed to open communication and encourages constructive stakeholder input regarding its activities.
Enquiries and comments concerning the EIB’s involvement in a project or the financing facilities, activities, organisation and objectives of the EIB, can be sent to the EIB Infodesk.
Alternatively, the EIB can be contacted through its external offices.
Queries regarding details of a specific project, in particular when it is under appraisal by the EIB, should preferably be addressed directly to project promoters.

Media enquiries

Media-related enquiries can be addressed to the EIB Press Office. Please also visit our Media information section.

Complaints mechanism

Any complaint regarding alleged maladministration can be lodged via the EIB Complaints Mechanism. The European Ombudsman acts as an independent external accountability mechanism of the EIB.

Zero tolerance against fraud and corruption

The EIB has a zero tolerance policy on fraud or corruption. To report allegations of fraud and corruption relating to EIB-financed projects, please contact the Fraud and Investigation division. All complaints will be treated as strictly confidential and handled in line with the EIB investigation procedures and the Anti-Fraud Policy.

Related publications