Release date: 16 February 2007
Promoter – Financial Intermediary
Ambatovy Minerals SA and Dynatec Madagascar SALocation
Description
Development and operation of a new large-scale open pit lateritic nickel ore mine, construction and operation of a 220km slurry pipeline for transporting fine ore, and a hydrometallurgical processing plant and refinery.
Objectives
Production of 60 000 t/y nickel metal and 5 600t/y cobalt.
Comments
Mining and Quarrying
Sector(s)
Proposed EIB finance (Approximate amount)
Approx EUR 200 - 230 million.
Total cost (Approximate amount)
Approx EUR 2 315 million.
Environmental aspects
An extensive Environmental and Social Impact Assessment (ESIA) has been completed by independent consultants, and has been submitted to Government and approved. An addendum has been produced and submitted for the slurry pipeline route.
Procurement
The EPCM contract has been awarded following international negotiations with the few engineering companies able to carry out such a project. The individual contracts will be awarded following international negotiation.
The sponsor is a private company operating in the mining sector: the procedures followed are in compliance with the Bank's Guide to Procurement.
Status
Signed - 22/08/2007
Disclaimer