The project, to be implemented from 2019 to 2024, will finance the construction, rehabilitation, extension and modernisation of several healthcare services and ortho-pedagogical facilities.
Objectives
The sub-projects will contribute to the 5-year capital investment programme to extend, update, replace and reorganise the existing mental healthcare infrastructure network.
Sector(s)
- Health - Human health and social work activities
Proposed EIB finance (Approximate amount)
EUR 50 million
Total cost (Approximate amount)
EUR 120 million
Environmental aspects
Hospitals are not specifically mentioned in the EIA Directive 2014/52/EU amending the Directive 2011/92/EU, though the project might be covered by Annex II of the Directive in relation to urban development. The compliance with requirements of the EIA Directive 2011/92/EU as amended by 2014/52/EU on Environmental Impact Assessment (EIA) and Habitats Directive will be verified during appraisal. It is expected that the project will bear wider benefits to the community as healthcare is an element of social cohesion and economic development.
Procurement
The promoter will have to ensure that contracts for the implementation of the project shall be tendered in accordance with the relevant applicable EU procurement legislation (Directives 2014/24/EU and/or 2014/25/EU and/or 2014/23/EU as well as Directives 89/665/EEC and 92/13/EEC) as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.
Status
Signed - 30/11/2020