Recherche Fr menu fr ClientConnect
Recherche
Résultats
5 premiers résultats de la recherche Voir tous les résultats Recherche avancée
Recherches les plus fréquentes
Pages les plus visitées
Référence: 20090322
Date de publication: 13 octobre 2009

Promoteur – Intermédiaire Financier

Ofgem - Office of the Gas and Electricity Markets (GB regulatory authority)

Lieu

Description

The operation would concern several, separated transmission connection projects for offshore wind farms located in UK waters. Ofgem has developed a new regulatory regime for offshore transmission systems, whereby the authority will licence new Offshore Transmission Owners (OFTOs) - to own and maintain these assets over a 20 year period.

Objectifs

The regulatory entities will operate and maintain offshore transmission assets essential to the export of electricity from offshore windfarms, the development of which supports EU and national targets for renewable energy.

Commentaires

In line with the Bank’s eligibility guidelines, only those networks not yet constructed will be considered for EIB funding. On this basis, these are expected to be Sheringham Shoal, Ormonde, Greater Gabbard, Thanet, Walney 1 and Walney 2

Secteur(s)

Montant BEI envisagé (montant approximatif)

Up to 50% of total eligible project cost associated with each individual OFTO.

Coût total (montant approximatif)

To be determined during appraisal

Aspects environnementaux

An offshore wind farm including its associated equipment such as the transmission system falls by virtue of its technical characteristics under Annex II of EIA-Directive 85/337/EEC (as amended). According to national regulations an offshore wind farm is subject to a full mandatory EIA including public consultation. Further details of the environmental due diligence procedures applied for each of the transmission assets considered eligible for being financed by the Bank, will be assessed by the Bank during appraisal to verify compliance with the Bank’s environmental policy.

Passation des marchés

The regulatory authority Ofgem runs a competitive tender process following publication of a contract notice in EUOJ to identify preferred bidders for future OFTOs. A long list of pre-qualified bidders was announced. The tender process allows for interested parties to bid for multiple projects, and tenders will be conducted separately for each qualifying windfarm development.

Statut

Signé - 21/10/2011

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Royaume-Uni Énergie