Date de publication: 24 juin 2015
Promoteur – Intermédiaire Financier
AB AMBER GRIDLieu
Description
sConstruction of a gas pipeline between Klaipeda and Kursenai
Objectifs
The project consists of the construction of a 110 km long DN800 gas pipeline and a maximum operating pressure of 54 bar, from Klaipeda up to Kuršenai. The project will allow the capacity enhancement of Klaipeda-Kiemenai pipeline in Lithuania.
Secteur(s)
- Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné
Montant BEI envisagé (montant approximatif)
EUR 28 million
Coût total (montant approximatif)
EUR 59 million
Aspects environnementaux
The project required an environmental impact assessment (EIA), which has already been approved by the competent authority.
Passation des marchés
The investment is subject to the procurement provisions defined in Directive 2004/17/EC for entities operating in the water, energy, transport and postal services sectors.
Statut
Signé - 21/12/2015
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).