    Reference: 20220716
    Release date: 16 May 2024

    Promoter – Financial Intermediary

    JSC ELEKTROPRIVREDA SRBIJE BELGRADE

    Location

    Description

    Rehabilitation of several large hydropower plants, construction of a 13 megawatt new hydro unit at the Potpec hydroelectric power plant , development and implementation of greenfield renewables

    Objectives

    The operation is a framework loan to finance promoter's key green investments for the period 2024-2030 with a view to increase ultimately the national share of renewables to the target set by 2030. The project tentatively consists of i) the rehabilitation of 239 megawatt (MW) power units in of three hydropower plants (Bistrica hydroelectric power plant (HPP), Potpec HPP and Djerdap HPP) which are totalling 428 MW, ii) the construction of a new 13 MW unit at Potpec HPP, iii) several greenfield renewables of which more than 120 MW solar plants and iv) the rehabilitation of 129 MW Vlasinske hydropower cascade.

    Sector(s)

    • Energy - Electricity, gas, steam and air conditioning supply

    Under Global Europe NDICI guarantee

    Under EFSD+ Guarantee

    Proposed EIB finance (Approximate amount)

    EUR 200 million

    Total cost (Approximate amount)

    EUR 408 million

    Environmental aspects

    The construction of new hydropower unit would fall under Annex I while the rehabilitation of hydropower units and other small components would usually fall under Annex II of the Environmental Impact Assessment (EIA) Directive 2014/52/EU, amending the EIA Directive 2011/92/EU. The latter Annex II components would require the competent national authority to determine the need for an Environmental Impact Assessment Environmental authorisation has been delivered to Djerdap II HPP rehabilitation. Bistrita HPP was screened out in 2019 by the competent Authorities. The Promoter resubmitted the project to the competent Authority as the scope had slightly increased from the original design. Potpec HPP rehabilitation received its authorisation in 2018. Due to changes in the project (construction of an additional unit IV), the Promoter is carrying out the EIA to be sent to the Competent Authorities in 2024 to obtain the environmental authorisation and the subsequent building permit. Based on preliminary information received, the project components are unlikely to entail any substantial adverse environmental or social impacts. The Bank will review the project's potential environmental and social impacts in line with its Environmental and Social Sustainability Framework upon new allocation request under the framework loan.

    Procurement

    The Bank will require the promoter to ensure that implementation of the project will be done in accordance with the Bank's Guide to Procurement and the relevant applicable EU public procurement rules. The promoter Elektroprivreda Srbije (EPS) is a state-owned electric utility company. Public procurement procedures as set in the Bank's Guide to Procurement will apply.

    Status

    Approved - 21/06/2024

    Milestone
    Under appraisal
    Approved
    21 June 2024

    Disclaimer

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The information and data provided on this page are therefore indicative.
    They are provided for transparency purposes only and cannot be considered to represent official EIB policy (see also the Explanatory notes).

    Related tags

    Serbia Energy