Date de publication: 16 juin 2009
Promoteur – Intermédiaire Financier
City of Sofia
Lieu
Description
Rehabilitation of three of the main traffic nodes of Sofia’s road network.
Objectifs
Improvement of the quality of circulation and road safety.
Secteur(s)
Montant BEI envisagé (montant approximatif)
Up to EUR 35 million.
Coût total (montant approximatif)
Up to EUR 70 million.
Aspects environnementaux
As a Member State, Bulgaria has harmonised its environmental legislation in line with the relevant EU Directives (85/337/EC, as amended, and 2001/42/EC). The schemes would most likely fall outside both Annex I and II of the EU EIA Directive, however this screening will be performed by the Competent Authority on a case-by-case basis. Details on each scheme will be checked at appraisal stage, when the relevant specific information is available and can be analysed.
Passation des marchés
The promoter is a public entity subject to EU Public Procurement rules. EU Directives (2004/18/EC and 2004/17/EC) have been transposed into national legislation. Tenders will be/have been organised in compliance with EU requirements, with publication of tender notices in the EU Official Journal for projects above thresholds. Procurement procedures are therefore satisfactory to the Bank.
Statut
Signé - 22/10/2009
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).