    Référence: 20170745
    Date de publication: 27 juillet 2018

    Promoteur – Intermédiaire Financier

    AL FANAR CO LTD

    Lieu

    Description

    The project consists of the financing of 21 wind farms with sizes ranging from 8 to 50 MW - for a total installed capacity of 547 MW (163 wind turbines), located in Andalucía, Asturias, Castilla la Mancha, Castilla León, Galicia y Navarra. The plants were awarded to the promoter during the third renewable energy auction that was held in Spain in 2017.

    Objectifs

    EIB financing for this operation is expected to have an important acceleration and demonstration effect. Indeed, it will be one of the first greenfield renewable energy projects to be financed in Spain after the moratorium in 2012 and the new regulatory framework - which came into effect in 2014. Besides, the present operation will contribute to the achievement of Spain 2020 targets for renewable energy and to the reduction of the CO2 emissions

    Secteur(s)

    • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

    Montant BEI envisagé (montant approximatif)

    EUR 44 million

    Coût total (montant approximatif)

    EUR 643 million

    Aspects environnementaux

    The project falls under the Annex II of the EIA-Directive (Directive 2014/52/EU amending the EIA Directive 2011/92/EU), and have been screened in by the competent authority, requiring EIA processes to be performed. The authorization procedure, including the need of EIA processes for the interconnection facilities, and compliance with EU EIA, Birds and Habitats directives will be further appraised in detail, in particular the need for a cumulative impacts assessment and the impacts on protected flora and fauna, including Natura 2000 sites.

    Passation des marchés

    The Bank will require the Promoter to ensure that contracts for the implementation of the project will be tendered in accordance with the relevant applicable EU procurement legislation: Directive 2014/23/EU / 2014/24/EU or 2004/18/EC / 2014/25/EU or 2004/17/EC, where applicable, as well as Directive 92/13/EEC or Directive 89/665/EEC, as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.

    Statut

    Signé - 11/07/2019

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Espagne Énergie