    Référence: 20220558
    Date de publication: 29 novembre 2023

    Promoteur – Intermédiaire Financier

    SOCIETATEA NATIONALA NUCLEARELECTRICA SA

    Lieu

    Description

    The project concerns the design and construction of a tritium removal facility to improve radiation safety at the nuclear power plant.

    Objectifs

    The aim is to remove radioactive tritium from reactor coolant and moderator and consequently to reduce radiation exposure of personnel, the radioactivity level of controlled releases and the amount of radioactive waste. After removal of tritium the reactor coolant and moderator can be safely reused. Therefore, the project will improve radiation safety, operational efficiency and environmental sustainability of the power plant, as well as occupational and public health and safety. It will allow simplified and more efficient planning and execution of regular maintenance works, the planned refurbishments and the final decommissioning of the nuclear units. Shortening the outage periods would result in incremental electricity production. In addition, the removed tritium as a rare radioactive isotope has significant strategic value as a critical material needed in the development process of another promising low-carbon power generation technology, nuclear fusion. Tritium is also required for some emerging technologies to produce nuclear medicine isotopes.

    Secteur(s)

    • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné
    • Eau, assainissement - Production et distribution d'eau; assainissement, gestion des déchets et dépollution

    Montant BEI envisagé (montant approximatif)

    EUR 145 million

    Coût total (montant approximatif)

    EUR 316 million

    Aspects environnementaux

    The project has been subject to an Environmental impact assessment (EIA) process including public consultations and the transboundary context. The potential impacts associated with the project include construction health and safety, hazardous materials and waste, workers exposure to harmful impacts, community impacts and stakeholder engagement. However, with mitigation measures implemented, including good construction practice measures, monitoring and remedial actions the effects on environment are not considered significant. The environmental benefits of the project include reduction of radioactivity level of controlled releases, amount of radioactive waste, and radiation exposure of personnel. The decision of the competent authority was issued in January 2023.

    Passation des marchés

    The promoter is a state-owned company operating in utilities sector (electricity). The Bank required the promoter to ensure procurement of the contracts for implementation of the project in accordance with the applicable EU public procurement legislation with publication of tender notices in the EU Official Journal, as and where required.

    Statut

    Signé - 22/12/2023

    Milestone
    À l'examen
    Approuvé
    Signé
    15 novembre 2023
    22 décembre 2023

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Roumanie Énergie Eau, assainissement