Date de publication: 7 juin 2016
Promoteur – Intermédiaire Financier
TEOLLISUUDEN VOIMA OYJLieu
Description
Investment in safety improvements including replacement of emergency diesel generators and reactor internal pumps, as well as introduction of a new additional emergency feedwater system at the Olkiluoto (Finland) nuclear power plant
Objectifs
The project will contribute to improvements in safety and reliability of low-carbon electricity supply.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 100 million
Coût total (montant approximatif)
EUR 227 million
Aspects environnementaux
Based on technical characteristics of the safety upgrade investment project schemes they will not require environmental impact assessments. The project works are planned to be implemented at an existing operational site and they are mostly related to replacement of existing equipment. The project activities are expected to have minimal environmental impact. The typically anticipated impact is mainly temporary and relates to construction and installation works and can usually be well managed by appropriate measures taken during project implementation.
Passation des marchés
The promoter is a private company operating in the utilities sector; however the electricity sector in Finland, based on an exemption granted by the European Commission, is not subject to EU rules on public procurement.
Statut
Signé - 30/09/2016
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).