Suche starten De menü de ClientConnect
Suche starten
Ergebnisse
Top-5-Suchergebnisse Alle Ergebnisse anzeigen Erweiterte Suche
Häufigste Suchbegriffe
Meistbesuchte Seiten
    Referenz: 20090576
    Veröffentlichungsdatum: 23 Februar 2010

    Projektträger – zwischengeschaltetes Finanzinstitut

    The Irish National Roads Authority (NRA)
    Michael Kennedy

    Ort

    Beschreibung

    The combined N17 /N18 Gort to Tuam PPP scheme is 57 km in length and commences at the northern extremity of the N18 Gort Crusheen scheme, which is currently under construction.

    Ziele

    This road will replace the existing single carriage-way road, much of which falls below NRA standard in terms of geometry, junction frequency, junction spacing and overtaking opportunities. It is expected that the introduction of the proposed road, with the 120 kph speed limit and superior standard, will result in significant improvements to safety and journey times.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    Up to EUR EUR 170 million.

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 530 million.

    Umweltaspekte

    The project falls under the requirements of Annex I of the EIA Directive 97/11/CE (amended by Directive 2003/35/EC), and is subject of a full Environmental Impact Assessment, including public consultation. Detailed analysis of the EIA process and the project impact and mitigation measures will be performed during appraisal, including assessment of impact on Natura 2000 sites and compliance to Habitats and Birds Directives.

    Auftragsvergabe

    The project is being procured as a Public Private Partnership. The PPP contract will be awarded under the competitive dialogue procedure applicable to public works contracts under EU Directive 2004/18/EC. The tender was published in the EU Journal on the 3rd of February 2009 (ref. 2009/S22-031253).

    Projektstatus

    Unterzeichnet - 30/04/2014

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Irland Verkehr