The project concerns the construction of a 220 kV, 270 km-long overhead transmission line and related substations interconnecting the currently isolated power systems of Antananarivo and Toamasina. The interconnexion will support the integration of large hydro power plants being developed in both systems.
Ziele
The project will contribute to increase the electricity access rate of the country (currently standing at 24%), as well as the reliability of supply.
Sektor(en)
- Energie - Energieversorgung
Garantie im Rahmen des Außenmandats
Cette opération est couverte par la Garantie ELM.
Under Global Europe NDICI guarantee
Dans le cadre de la garantie EFSD+
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 81 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 193 million
Umweltaspekte
The project will have adverse environmental and social impacts. The EIB will ensure that appropriate measures are taken to protect the environment and the rights of the project affected people and to avoid, reduce, mitigate, compensate and remedy the impacts. The promoter has identified all relevant environmental and social impacts and risks and has developed and ESMP to manage the impacts, according to EIB Environmental and Social standards and requirements.
Auftragsvergabe
The Bank will require the promoter to ensure that implementation of the project will be done in accordance with the Bank's Guide to Procurement.
Projektstatus
Unterzeichnet - 29/11/2021
Haftungsausschluss